Water Channel Construction and Repairing Works at Besiktasm naat


Location Istanbul
Project Completion Date: 06.01.2004
Client: Istanbul Water and Wastewater Management 

Project Description:
18.335 m in length with the diameters between 100-250 mm ductile font pipes laid out, 1.151 times with the diameters of 32-40 mm residential water connections done, 35.194 m in length of residential water connections repaired, 18.053 m in length and the diameters between 200-600 mm concrete wastewater pipe lines construction, 34.120 m in length with the diameter of 200 wastewater residential connections constructed, 2.011 times sewage truck used, 2.357 times clogged wastewater channels cleared, 5.651 times clogged residential connections cleared.